The Regulation Amending the Electricity Market License Regulation was published in the Official Gazette and entered into force.
Accordingly, a temporary article has been added to the Electricity Market Licensing Regulation, which covers the obligations regarding the provision of guarantees in pre-license applications for storage electricity generation facilities.
Within the scope of the Temporary Article, regarding the obligation to provide guarantees for the applications for which a connection opinion has not been formed yet from the pre-license applications made until 30 June 2023, the obligation to provide a guarantee for the applications for which a positive connection opinion has been formed by TEIAS is within 30 days from the date of notification of the notification made by the Energy Market Regulatory Authority to the company. needs to be fulfilled.
If the obligation is not fulfilled within the said period, the pre-license application will be rejected by the decision of the Board.
In addition, the Regulation on the Amendment of the Electricity Network Regulation was published in the Official Gazette and entered into force. Some articles of the Electricity Network Regulation were amended.